|
R
| |
LATEST UPDATE 20 July 2007 (unchanged since 4 June)
Star Energy currently plans to further appraise the Albury
gasfield by drilling from its existing site in Albury Park. They also plan
to use the Albury gasfield to develop extensive gas storage facilities. Further
details are given below but in summary there are currently 3 phases of proposed
development that will affect Albury Park:
-
APPRAISAL OF ALBURY 2
Star Energy needs two appraisal wells to assess a new "horizon" of the
Albury gasfield. This new horizon is known as "Albury 2" and is
thought to be 4 times bigger than the horizon that has already been depleted
"Albury 1".
-
GAS STORAGE OF ALBURY 1
Star Energy now plans to site gas storage facilities at Furze Copse near
Send prison, rather than in Albury Park. However, the gas storage plans will
require the drilling of 4 additional development wells from a slightly
enlarged site at Albury Park plus a 5 mile pipeline to Furze Copse.
-
GAS STORAGE OF ALBURY 2
If appraisal of Albury 2 confirms expectations, Star Energy will submit
plans to use Albury 2 for gas storage, hence increasing storage capacity by
up to 500%. This would require the drilling of an unspecified number
of additional wells in Albury Park.
.


 |
GAS STORAGE OF ALBURY 1
Star Energy's has recently confirmed that in the summer they will
also be submitting plans for gas storage of the depleted horizon Albury 1.
They will be submitting these plans to the dti using the 1965 Gas Act to
circumvent local planning procedures. Star Energy initially planned to
use Albury Park for building their gas storage processing facility but now
seem to realise that this level of industrialisation is unacceptable in an
AONB. At the end of May, Star Energy revealed that they now plan to
build this facility at Furze Copse 800m east of Send prison.
There would be 5 elements to Phase 1 Gas Storage application:
1. 4 additional development drill wells in Albury Park
2. pipeline from Albury Park to Furze Copse Gas Storage site. Would go west
of New Road then cross to east of new rd to go under A25 then north to east
of Sherbourne Farm. N.B. not West of Landfill site as stated in the
Star Energy briefing. Pipeline would be 32” diameter and capable to
taking Phase 1 & 2. 26m construction width, 5mile long. 1m min depth. 6mth
construction, 6m restoration.
3. Pipe storage area (temporary) south of main road at East Clandon.
4. Furze Copse Gas Storage site 800m east of perimeter of Send prison. 10
acre site area with plant occupying 3acres.
5. pipe connection north from Gas storage plant to Ripley gas connection
near Ockham.
Star Energy will commission an Environmental Impact Assessment and has
produced a
detailed
EIA scoping report. Star Energy welcomes comments on the
proposed scope to help ensure that the EIA considers all environmental
issues relevant to the project. The scoping document is
available in hard copy and should be available soon on the Star Energy
website. Enquiries & comments should be directed to
Paul Dacombe, Consents
Manager at Star Energy.
|
 |
GAS STORAGE OF ALBURY 2
If appraisal of Albury 2
confirms expectations, Star Energy will submit plans for phase 2
development of Albury 2 for gas storage. These plans would
utilise the gas processing facility at Furze Copse and the pipeline from
Albury Park to Furze Copse. An additional pipeline would be required
from Furze Copse to Tatsfield.
Gas storage of Albury 2 would required an
unspecified number of development wells in be drilled, in addition to the
two Albury 2 appraisal wells and four Albury 1 development wells. Each
well would take up to 9 weeks to drill and is likely to cause significant
noise disturbance in the AONB. |
 |
What about Blackheath Common ?
Star Energy gave unequivocal reassurance at a meeting of the Community
Liaison Panel on 24th May that they would not drill wells on Blackheath
Common. They have also confirmed this in writing. |
RETURN
TO UPDATE PAGE
|